plan of baltic pipeline system-ii
the initial capacity of pipeline @ first stage 10 million tons of oil per year, upgraded 50 million tons during second stage. of this, 12 million tons transported ust-luga , 12 million tons kirishi refinery. diameter of pipeline vary between 1,020 , 1,067 millimetres (40 , 42 in).
the construction cost estimated @ us$4 billion. second stage expected completed december 2013.
the pipeline have 8 pumping stations. during first stage, 2 new pumping stations built, , 2 pumping stations (in unecha , andreapol) renovated. during second stage, 4 new pumping stations added, , pumping station №7 equipped tank farm capacity of 80,000 cubic metres (2,800,000 cu ft). in addition, oil terminal in ust-luga built.